New IT project failure metrics: is Standish wrong?

Posted by Michael Krigsman @ 11:39 am

Categories: CIO issues, IT issues, Project management, Project strategy, Research and statistics

Tags: Project, Volatility, Information Technology, Author, Project Manager, Standish Group, Investment, Strategy, Finance, Management

The Standish Group’s Chaos Report describes two-thirds of IT projects as being “challenged.” Now, three academics have published a report suggesting these numbers are flawed, and that only one-third of IT projects actually fail. If this new report is accurate, it represents a significant departure from common perceptions of IT project risk and failure. The research was conducted by Chris Sauer, Andrew Gemino, and Blaize Horner Reich who described their results in an article titled, The impact of size and volatility on IT project performance.

EXECUTIVE CONCLUSIONS

The following table outlines management recommendations made by the authors on the basis of their research:

New research into IT failure rates

DIFFERENCES RELATIVE TO PREVIOUS RESEARCH

To understand why the results differ from Standish, I asked Blaize Horner Reich, one of the authors, to explain. Blaize sent me unpublished material describing differences between her group’s methodology and that used to create the Chaos Report, which remains the most widely-quoted measure of software development failures.

In contrast to Standish, Blaize and her colleagues used project managers, rather than executives, as respondents. Since project managers typically have more detailed and specific project knowledge than do executives, this should yield more accurate and detailed research results. In addition, the group only researched most recent projects, presumably reducing the effect of poor memory on their findings.

New research into IT failure rates

A second important difference between the new research and Standish derives from assumptions made by the authors regarding the best way to classify IT projects. Instead of following the Standish model, which characterizes projects as failed/challenged/successful, the authors used a more finely-grained classification system, which emerged as they analyzed the data.

New research into IT failure rates

Here is a list of the failure/success categories that arose out of the research:

New research into IT failure rates

MEASUREMENT VARIABLES AND DATA

The authors examined two primary measures as determinants of project risk: size and volatility.

Project Size

The authors measured size according on the basis of four dimensions:

  • Effort (measured in person-months)
  • Duration (measured in elapsed time)
  • Team size
  • Budget

In summarizing the impact of size-related factors on project performance, the authors write:

Overall, increases in the size of a project mean increased risk, even for experienced project managers. However, conventional wisdom that restricts project size using budget or duration is somewhat misguided. A focus first on effort, then on team size and duration will limit risk of underperformance.

Surprisingly, we found that one-quarter of projects underperform however small their size. Even projects with budget less than £50,000, effort less than 24 person-months, duration shorter than six months, or team size of less than five experienced 25% risk. There is a significant level of risk regardless of size.

This size data is reported in the tables below:

New research into IT failure rates

Volatility

Project volatility was measured along two dimensions:

  • Governance volatility (measured by changes in project manager or
    executive sponsor)
  • Target volatility (measured by changes in schedule, budget, and scope).

The authors summarize volatility as a determinant of failure:

Projects with no change in key personnel faced a 22% risk of underperforming, whereas projects with two or more changes faced a risk of more than 50%. Projects with nine or fewer target changes faced no more than a 33% risk of underperforming whereas projects with more than nine changes faced a risk over 50%. These results suggest volatility is strongly related to performance, and indicate the importance of project governance.

The data regarding volatility is show below:

New research into IT failure rates

AUTHORS’ SUMMARY CONCLUSIONS

The authors offer these managerial insights:

Our results indicate that while approximately 9% of IT projects are abandoned, another 7% consistently overdeliver on original project targets.

What our results suggest is that IT project managers cannot accept all of the responsibility of delivering projects successfully. Top management and steering committees have a significant role to play in managing project risk. Ambitious-sized projects, moving targets, and managerial turnover present challenges for IT projects that stretch even experienced project managers and result in greater variances. Effective oversight of projects can help project managers respond to these challenges.

MY CONCLUSIONS

This research is serious, credible, and cannot be ignored. In addition, it’s consistent with other recent studies of IT failure. I recommend following the authors’ work to see how it develops over time.

As the authors correctly assert, IT failure rates remain high, and responsibility for success clearly lies with both executive management and the project team. The risk reduction strategies outlined in the executive conclusions table (at the top of this post) are well-considered and should be followed by organizations implementing IT projects.

Although the research methodology and data may differ from previous studies, the management conclusions and action items are fundamentally in accord with best practices for avoiding failed IT projects.

Michael KrigsmanMichael Krigsman is CEO of Asuret, Inc., a software and consulting company dedicated to reducing software implementation failures. Click here to discuss this post with him on Twitter. See his full profile and disclosure of his industry affiliations.

Email Michael Krigsman

Subscribe to IT Project Failures via Email alerts or RSS.

  • Talkback
  • Most Recent of 8 Talkback(s)
The definition of IT implementation failure
Unfortunately we really only hear about big projects that have failed. And the definition of "failed project" is not universal. Is it a time or budget blow out or under delivered agreed upon benefits ... (Read the rest)
Posted by: Corporate profiling Posted on: 02/29/08 You are currently: a Guest | | Terms of Use
Failure rates  tinfoil hat | 12/07/07
Excellent point  mkrigsman@...ZDNet Moderator | 12/07/07
Another good observation  mrichardson14287@... | 12/11/07
RE: New IT project failure metrics: is Standish wrong?  SWMCinci | 12/11/07
Obvious Omission in Discussion  JZepp | 12/11/07
What's the target  zdnet@... | 12/11/07
both are correct  Chomps | 12/12/07
The definition of IT implementation failure  Corporate profiling | 02/29/08

What do you think?

SponsoredWhite Papers, Webcasts, and Downloads

advertisement

Recent Entries

advertisement

Archives

ZDNet Blogs

White Papers, Webcasts, and Downloads

  • Smart Tech Expert advice on innovations in healthcare and the green technologies that make it happen. Find out more
  • Smart Business Discussion and advice on management issues that revolve around making your world smarter and more useful. More Smart Advice
  • Smart People The best and worst moves in the management and strategy trenches. Learn More